Soleos Energy
Third Party Open Access

Consumers • Procurement Routes

Third-Party Open Access

Buy Green Power, Zero Investment. Purchase solar power from an independent generator via the grid. No ownership, no project risk, no capital outlay — just sign a PPA and start saving.

₹0

Investment

15-30%

Cost Savings

Zero

Asset Risk

2-4 wks

Go Live

Overview

What is Third-Party Open Access?

Third-Party Open Access is a framework under the Electricity Act 2003 allowing consumers to purchase power from any generator by using the grid as a common carrier.

Solar Generator

Injects power

Grid Network

STU / DISCOM

Your Factory

Draws power

You pay generator for solar power at negotiated tariff, and pay DISCOM/STU for network usage. Net cost is typically 15-30% lower than grid tariff.

Value Proposition

Why Third-Party Open Access?

Zero Capital Investment

No equity, no financing, no asset on balance sheet. Simply sign a PPA and start receiving solar power.

₹0

Immediate Savings

Solar tariff plus OA charges still 15-30% lower than grid tariff. Savings from day one.

15-30%

Zero Operational Risk

No ownership means no asset risk, no O&M responsibility, no performance risk.

Zero Risk

Fast Deployment

Tie-up with existing plants. Skip 6-12 month development. Go live in 2-4 weeks.

2-4 wks

Flexibility

Easy to scale up by adding PPAs. Shorter contracts (10-15 years). Exit provisions available.

Flexible

Green Credentials

Receive I-RECs for consumption. Meet RE100, CDP, SBTi with verifiable renewable energy.

100%

The Process

How It Works

01

Identify Generator

We connect you with IPPs having available capacity in your state.

02

Negotiate PPA

Agree on tariff, tenure (10-25 years), minimum offtake, terms.

03

OA Application

Apply for open access with SLDC, submit BG, scheduling agreement.

04

Metering

Install ABT-compliant meters at drawl point.

05

Scheduling

Generator submits day-ahead schedule, you draw scheduled power.

06

Billing

Receive bills for solar power + wheeling + CSS/AS + SLDC fees.

State Analysis

Open Access by State

StateTotal OA ChargesAssessment
Karnataka₹0.97-1.17Excellent
Rajasthan₹0.55-1.72Good
Gujarat₹1.55-2.05Moderate
Maharashtra₹2.85-4.15Challenging
Tamil Nadu₹1.50-2.50Moderate
Andhra Pradesh₹3.05-4.20Challenging
Telangana₹2.00-3.05Moderate
Madhya Pradesh₹1.43-1.98Good

*Indicative for FY 2024-25. Subject to SERC revisions.

Key Considerations

What You Should Know

CSS & AS Applicable

Unlike captive, third-party attracts full CSS and AS. Can be ₹1-4/kWh in some states.

Same State Preferred

Intrastate is simpler and cheaper. Interstate involves additional charges and complexity.

No Depreciation

Since you don't own the asset, no depreciation benefit under Income Tax Act.

Regulatory Uncertainty

OA charges revised annually by SERCs. PPA should have charge pass-through provisions.

Minimum Offtake

PPAs require minimum offtake (70-80%). Liable for minimum charges if consumption drops.

Scheduling Discipline

Day-ahead scheduling mandatory. Deviations attract UI charges.

Comparison

Third-Party vs Captive

FeatureThird-PartyCaptive
InvestmentZero26-100%
Savings15-30%30-60%
CSS/ASApplicableExempt
RiskZeroOwnership risk
DepreciationNo40% Y1
ControlNoneFull/Partial
Deploy Time2-4 weeks6-12 months
ExitEasierHarder

Implementation

Getting Started

End-to-end timeline: 2-4 months

01

Assessment

1-2 weeks

Analyze load profile, demand, voltage level

02

State Review

1 week

Evaluate OA charges, banking, regulations

03

Generator Matching

2-3 weeks

Shortlist suitable IPPs

04

PPA Negotiation

2-4 weeks

Finalize tariff, terms, clauses

05

OA Application

4-8 weeks

SLDC registration, agreements

06

Go Live

2-3 weeks

Meters, testing, billing start

Questions

Frequently Asked Questions

What is minimum consumption for open access?

Most states require 1 MW contracted demand. Some allow 500 kW or 100 kW for renewables.

Can I source from another state?

Yes, via ISTS. But involves additional charges and complexity. Intrastate recommended.

What if generator fails to supply?

You draw from grid at normal tariff. Generator may owe compensation per PPA terms.

How is billing structured?

Two bills: (1) Generator for solar energy, (2) DISCOM for wheeling, CSS, AS, standby.

Can CSS/AS change during PPA?

Yes, revised annually. PPA should have charge pass-through provisions.

What is banking?

Bank excess energy with DISCOM to draw later. Charges 2-10% of banked energy. Not all states allow.

How does this compare to rooftop solar?

Rooftop gives 40-60% savings with investment. Third-party gives 15-30% with zero investment.

Can I combine with captive?

Yes, many do both — rooftop for base load, third-party OA for additional green power.